Pune Ring Road Package-Wise Bids: MEIL, NECL, PNC, GRIL & RSIIL Win Contracts

The much-anticipated Pune Ring Road project has taken a significant step forward as the Maharashtra State Road Development Corporation (MSRDC) opened financial bids for its 136.8 km access-controlled highway. Spread across Pune’s eastern and western taluks, this mega-project is a critical urban infrastructure development aimed at easing congestion, improving regional connectivity, and reducing long-distance freight traffic within Pune city.

After months of evaluation, five major contractors — Megha Engineering and Infrastructures Ltd. (MEIL), Navayuga Engineering Company Ltd. (NECL), GR Infraprojects Ltd. (GRIL), PNC Infratech Ltd., and Roadway Solutions India Infra Ltd. (RSIIL) — have emerged as the lowest bidders for nine of the project’s twelve packages.

This blog takes a deep dive into the package-wise bidder details, bid values, and the larger implications for Pune’s transport infrastructure.


Background of the Pune Ring Road Project

The Pune Ring Road is designed as a 4–6 lane access-controlled highway, planned to decongest urban traffic by diverting intercity and heavy vehicles away from Pune’s crowded roads.

  • Project Length: 136.8 km
  • Implementing Agency: Maharashtra State Road Development Corporation (MSRDC)
  • Configuration: Divided into 12 civil packages – 7 in the Eastern Ring Road (ERR) and 5 in the Western Ring Road (WRR)
  • District Coverage: Khed, Haveli, Purandar, Bhor, Mulshi, and Maval taluks
  • Tendering Timeline:
    • RfQ Applications Invited: April 2023
    • RfQ Opened: June 2023 (28 firms applied)
    • RfP Round: December 2023 (18 firms qualified)
    • Financial Bids Submitted: April 2024 (26 bids from 12 firms)
  • Construction Deadline: 900 days (approx. 2.5 years)

With Pune rapidly urbanizing, this road is not just a bypass but also a logistics backbone that will support industrial hubs and improve connectivity to Mumbai, Satara, Ahmednagar, and other regions.

Pune Ring Road
Pune Ring Road

Package-Wise Bid Results

Here’s a detailed package-wise breakdown of bidders, their bid values, and the lowest bidder for each contract.


Package E1 – Urse to Indori (11.85 km)

BidderBid Value (₹ Cr.)Lowest Bidder
Megha Engineering2524.92Megha Engineering
Navayuga Engineering2633.00

Estimated Cost: ₹1805 Cr
Observation: MEIL’s winning bid was 39.88% higher than MSRDC’s estimate, reflecting the rising cost of construction materials and execution challenges.


Package E2 – Indori to Chimbali (13.80 km)

BidderBid Value (₹ Cr.)Lowest Bidder
PNC Infratech2486.00PNC Infratech
Welspun2548.90
HG Infra2586.11
L&T2612.80
J Kumar Infra2626.00

Estimated Cost: ₹1706 Cr
Observation: PNC’s bid is 45.72% higher than MSRDC’s estimate, showing a sharp deviation between projected and actual costs.


Package E3A & E3B – Chimbali to Lonikand (21.20 km)

BidderBid Value (₹ Cr.)Lowest Bidder
Megha Engineering2756.86Megha Engineering
Navayuga Engineering2855.00

Estimated Cost: ₹1991 Cr
Observation: MEIL further consolidated its presence in the eastern corridor by bagging this long stretch.


Package E4 – Lonikand to Walti (24.50 km)

BidderBid Value (₹ Cr.)Lowest Bidder
Roadway Solutions2251.00Roadway Solutions
GR Infra2316.07
APCO Infratech2342.00
PNC Infratech2396.00

Estimated Cost: ₹1732 Cr
Observation: A breakthrough for RSIIL, a relatively smaller player compared to MEIL and NECL, winning one of the longest stretches.


Package W1 – Urse to Kemsewadi (14.65 km)

BidderBid Value (₹ Cr.)Lowest Bidder
Megha Engineering2661.79Megha Engineering
Navayuga Engineering2775.00

Estimated Cost: ₹1904 Cr
Observation: MEIL bagged another key package, strengthening its hold on WRR.


Package W2 – Kemsewadi to Morewadi (20.00 km)

BidderBid Value (₹ Cr.)Lowest Bidder
Navayuga Engineering2702.00Navayuga Engineering
Afcons Infrastructure2824.00
Megha Engineering2884.00

Estimated Cost: ₹1975 Cr
Observation: NECL marked its first western section win, beating Afcons and MEIL.


Package W3 – Morewadi to Vardade Khamgaon (14.00 km)

BidderBid Value (₹ Cr.)Lowest Bidder
Navayuga Engineering2696.00Navayuga Engineering
Megha Engineering2812.00
Afcons2874.00

Estimated Cost: ₹1980 Cr
Observation: NECL’s competitive pricing allowed it to win back-to-back WRR packages.


Package W4 – Vardade Khamgaon to Kalyan Rahatwade (7.50 km)

BidderBid Value (₹ Cr.)Lowest Bidder
Navayuga Engineering2724.00Navayuga Engineering
Afcons2823.00

Estimated Cost: ₹1992 Cr
Observation: NECL bagged its third western package, signaling a strong comeback.


Package W5 – Kalyan Rathwade to Shivare Kusgaon (9.30 km)

BidderBid Value (₹ Cr.)Lowest Bidder
GR Infra1997.07GR Infra
Gawar2089.00
HG Infra2122.11

Estimated Cost: ₹1533 Cr
Observation: GRIL secured one package in WRR, ensuring its participation in the project.


Summary of Wins

ContractorPackages WonKey Stretches
Megha Engineering3E1, E3A/B, W1
Navayuga Engineering4W2, W3, W4, close second in others
PNC Infratech1E2
GR Infra1W5
Roadway Solutions1E4

Challenges Ahead

While the bidding process is complete, the project faces a serious financial hurdle. The lowest bids are 30–45% higher than MSRDC’s estimates, creating a funding deadlock.

  • E1 Example: MEIL’s bid was ₹2524.92 Cr vs. an estimate of ₹1805 Cr (≈ 40% higher).
  • E2 Example: PNC’s winning bid was 45.72% above estimates.

Unless MSRDC increases its project budget or alters the project scope, there is a risk of delays or even re-tendering.


Why Pune Needs the Ring Road

  1. Traffic Decongestion: Will divert heavy vehicles, reducing inner-city jams.
  2. Regional Connectivity: Links industrial hubs in Chakan, Talegaon, and Hinjawadi.
  3. Economic Growth: Eases logistics, benefiting Pune’s IT and auto sectors.
  4. Environmental Benefits: Less city traffic means reduced emissions.

MSRDC on Tuesday also opened bids for 5 other expressway projects – and things don’t look too bright for them either. Check out each link below for a list of winners: